Thanks for clarifying.
This is a new plant that will be in ECC in the coming months; not existing when I originally did the setup tables. Once the new plant is online, please confirm that I need to go through the setup steps again and delete the setup tables, then only fill the setup tables with the new plant. Then that plant will start coming across with the already existing delta load and will be picked up with the ECC job LIS-BW-VB_APPLICATION_04_200?
Thanks for the help.