Hi,
Thank you,
Already I reproduced the issue with help of PP & Functional consultant Team.
Still I will confirm ,Whether they do standard way of reversing or etc.
Just fYI, SAP do come up with bugs, and might be I am the first person to get the issue and start thread!!! But as I mentioned in my first message some one got the same issue long back but didn't post the solution in that thread - last message answered by srikanthhttp://scn.sap.com/thread/357662
I will Update you if I get any solution or someone updates me.
In parallel I am getting some workaround to get the planned Quantity from the first level of operation by considering yield + scrap+ rework as per my client business scenario.
Thank you!!!
Lets look for solution !!